Wednesday, March 11, 2026

Good News From GoodNews Christian School

Hey Friends,

Thanks for joining me today. I have an update on the school in Nigeria. They are working hard to complete the latest building phase. 

We are excited for their progress. Our plan is to help them with the money needed to complete the building. Also, we would love to help them with funds to furnish it!

BFM has recently received some donations for the school. We sincerely appreciate every generous gift. The funds will go to help our friends in Nigeria!
 
I will let an update of Bro. Shobanke’s email close out this post.

Odie

Please find below a brief update on the progress of the work so far:

Ground Floor: Fully completed—plastered, with doors and windows installed.

First Floor: Plastering completed; doors and windows installed; railings fixed.

Second Floor: Roofing completed; doors and windows installed; railings fixed; ceiling fully completed. 






The major remaining aspects of the project are the exterior plastering and plumbing fixtures, which the cost is around $4,000 dollars. 